IMPROVING THE CLUBHOUSE:
PLEASE READ
As previously advised, we are improving our clubhouse. Please note the following intended schedule of works over the next three weeks. During this time the changing rooms will be out of action and we will have portaloos in place.
Please advise any visitors you may be expecting.
Please bear with us, your volunteer committee, as we commission this work to improve your facilities.
4th/5th November:
- Site set up, decommission. Toilets (portaloos) delivered.
- Skip delivered
6th/7th/8th November:
- Build new shower areas
- Run new pipe work for plumbing and heating. First fix of electrics.
- Plasterboard shower areas.
- Plaster skim appropriate areas.
Week of 11th November:
- Windows and doors installed
- Tiling to shower areas
- Second fix of electrics and plumbing
Week of 18th November
- Flooring installed changing rooms
- Decoration to internals. Professional mastic seal
- Skip removed
- Toilets (portaloos) removed
- Site handover.
Any queries please contact secretary@epsomtennisclub.co.uk
Thanks.